NEW QUESTION 23
Which purpose relates to the instrumental Success Factors?

  • A. Inform the development of the Terms of Reference
  • B. Informs the development of the Business Case
  • C. Underpins the prioritization of requirements
  • D. Positions DSDM projects for a successful outcome

Answer: B

 

NEW QUESTION 24
Which of the following is a DSMD principle?

  • A. Build incrementally
  • B. Build incrementally in Timeboxes
  • C. Build incrementally from Feasibility onwards
  • D. Build incrementally from firm foundations

Answer: D

 

NEW QUESTION 25
Which plain defined by DSDM, has a planning horizon that includes the end of a project?

  • A. High-Level
  • B. Detailed
  • C. Delivery
  • D. Timebox

Answer: C

 

NEW QUESTION 26
Which of the following are recognized DSDM styles of Timebox?
1. Unstructured
2. Consolidated

  • A. Only 2 is true
  • B. Neither 1 or 2 is true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

Answer: C

 

NEW QUESTION 27
What does DSDM refer to the Minimum Usable Subset?

  • A. All requirements in the functional specification
  • B. The Must Have requirements
  • C. Those requirements that have passed user acceptance testing
  • D. The Must, Should and Could have requirements

Answer: B

 

NEW QUESTION 28
When using the Iterative Development technique, which of the following should each cycle include?
1. Though
2. Action
3. Control
4. Conversation

  • A. 1, 2, 4
  • B. 2, 3, 4
  • C. 1, 3, 4
  • D. 1, 2, 3

Answer: C

 

NEW QUESTION 29
Which phase in the DSDM process aims to understand the scope of work and, in broad terms, how it will carried out, by whom, when and where?

  • A. Evolutionary Development
  • B. Pre-Project
  • C. Foundations
  • D. Feasibility

Answer: C

 

NEW QUESTION 30
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.

  • A. Made collaboratively
  • B. Share between all of the project roles
  • C. The responsibility of the Business Sponsor
  • D. Viewed in light of the overriding project goal

Answer: A

 

NEW QUESTION 31
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?

  • A. Terms of Reference
  • B. Delivery Plan
  • C. Management Approach Definition
  • D. Foundation Summary

Answer: D

 

NEW QUESTION 32
Which of the following statements about the technical Coordinator role is true?
The technical Coordination provides the same function from a technical perspective as the Business Ambassador does from a business perspective.
The technical Coordinator is responsible for ensuring that the solution confirm to the requested technical standards.

  • A. Both 1 and 2 are true
  • B. Only 2 is true
  • C. Neither 1 or 2 is true
  • D. Only 1 is true

Answer: B

 

NEW QUESTION 33
In what phase is it first established whether further investigation of the project is justified?

  • A. Evolutionary Development
  • B. Pre-Project
  • C. Foundations
  • D. Feasibility

Answer: D

 

NEW QUESTION 34
How is contingency typically managed in a DSDM project?

  • A. Allowed adding a percentage to the high-level estimates.
  • B. Not needed in a DSDM project.
  • C. Managed by varying the features to be delivered.
  • D. Managed by varying time and cost

Answer: C

 

NEW QUESTION 35
Which statement about change is correct for DSDM?

  • A. Avoid change whenever possible
  • B. Change is a symptom of an inability to define requirements properly
  • C. Project operate with a changing world
  • D. Change is inevitable and males estimating very difficult

Answer: C

 

NEW QUESTION 36
What phase will create Solution increments?

  • A. Foundations
  • B. Evolutionary Development
  • C. Deployment
  • D. Feasibility

Answer: B

 

NEW QUESTION 37
Which purpose relates to the Consolidation in a structured Timebox?

  • A. To formality accept the structured Timebox deliverables.
  • B. To address the requirements and test the structure Timebox product.
  • C. To tie up any loose ends related to Evolutionary Development
  • D. To confirm the detail of all the requirements to be delivered by the structured Timebox.

Answer: D

 

NEW QUESTION 38
In a free format Timebox, when should reviews take place?

  • A. Throughout the body of the Timebox.
  • B. After the Timebox has been completed
  • C. During the Close.Out phase
  • D. During the Kick-Off phase

Answer: A

 

NEW QUESTION 39
......