C-TS422-2020 Exam Questions Get Updated [2021] with Correct Answers
Practice C-TS422-2020 Questions With Certification guide Q&A from Training Expert ValidBraindumps
NEW QUESTION 14
What does it mean for the production planner when MRP works with infinite capacities?
- A. MRP creates capacity requirements only if the work center has sufficient capacity.
- B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
- C. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
- D. MRP creates capacity requirements without checking the capacity of a work center.
Answer: D
NEW QUESTION 15
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.
- A. Production version
- B. Work center
- C. Plant
- D. Material
Answer: B,D
NEW QUESTION 16
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stockis zero and the discontinuation date is in the past?
- A. Kanban
- B. Production order release
- C. Material requirements planning
- D. Back flushing
Answer: C
NEW QUESTION 17
In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.
- A. Planning mode (bucket/sequence)
- B. Direction (forward/backward)
- C. Fixed pegging (on/off)
- D. Finiteness level (0...1)
- E. Scheduling control (finite/infinite)
Answer: A,B,E
NEW QUESTION 18
How would you define pegging in the context of Advanced Planning?
- A. An evaluation that is ordered according to thebill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
- B. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
- C. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
- D. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
Answer: A
NEW QUESTION 19
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a positive offset time in the strategy profile.
- B. Specify a negative offset time in the strategy profile.
- C. Specify a positive planning horizon in the strategy profile.
- D. Specify a negative planning horizon in the strategy profile.
Answer: B
NEW QUESTION 20
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Replenishment strategy
- B. Control cycle
- C. Production supply area
- D. Rate routing
Answer: B
NEW QUESTION 21
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Creation of dependent requirements
- B. Change of the storage bin
- C. Change of the material'sprocurement type
- D. Creation of a purchasing contract
- E. Creation of a sales order
Answer: A,C,E
NEW QUESTION 22
An issue storage location was NOT found through the work center, bill of material (BOM)item, or material master. Whatdetermines whether the storage location can be derived from the production version?
- A. MRP Profile
- B. MRP Controller
- C. MRP Group
- D. Plant Data
Answer: C
NEW QUESTION 23
What are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 3 correct answers to this question.
- A. Create object selection variant for product-related alerts.
- B. Create object selection variant for transportation lane-related alerts.
- C. Assign the overall profile to the authorization profile.
- D. Create object selection variant for resource-related alerts
- E. Assign the alert profile to the overall profile.
Answer: A,D,E
NEW QUESTION 24
Which of the following business processes are controlled by parameters that are dependent on production order type? Note: There are 2 correct answers to this question.
- A. Engineering change management
- B. Planning
- C. Implementation
- D. Inspection during production
Answer: B,C
NEW QUESTION 25
Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers tothis question.
- A. Maximum stock level
- B. Lot size
- C. Purchase orders
- D. Safety stock
Answer: B,D
NEW QUESTION 26
What does the industry sector determine? Note: There are 2 correct answers to this question.
- A. Whether material numbers are assigned internally or externally
- B. Whether a material master fieldis required, changeable, displayed, or hidden
- C. Which transaction you can use to create a new material
- D. Which material master views can be maintained
Answer: B,D
NEW QUESTION 27
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP"/OS)?
- A. Use a planning group.
- B. Use a propagation range.
- C. Use a resource group.
- D. Use a heuristic.
Answer: D
NEW QUESTION 28
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?
- A. Supply Network Planning (SNP)
- B. Capacity Requirements Planning (CRP)
- C. Material Requirements Planning (MRP)
- D. Demand Planning (DP)
Answer: C
NEW QUESTION 29
Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.
- A. Co-products
- B. Waste products
- C. Continuous flow materials
- D. Bulk materials
- E. By-products
Answer: A,B,E
NEW QUESTION 30
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Scrap percentage
- B. Installation point
- C. Item type
- D. Quantity
Answer: B,D
NEW QUESTION 31
What are some uses for the low-level code assigned to each material? Note: There are 2correct answers to this question.
- A. It is used by product costing to determine how costs are rolled up.
- B. It is used in MRP to determine the sequence in which materials are planned.
- C. It is used by engineering to identify sub items in an engineering bill of material(BOM).
- D. It is used by ATP to determine the priority of alternative components.
Answer: A,B
NEW QUESTION 32
Which actions does the system perform by default when you save aconfirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
- A. Material staging for next order in sequence
- B. Posting of goods receipt for the product
- C. Posting of production costs to the production cost collector
- D. Archiving of documents for assembly scrap
- E. Reduction of associated capacity requirements
Answer: B,C,E
NEW QUESTION 33
If you use floats to limit dispatching in capacity planning, what type of time element can be reduced by strategy settings while dispatching?
- A. Production time
- B. Minimum wait time
- C. Goods receipt processing time
- D. Queue time
Answer: D
NEW QUESTION 34
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.
- A. Product-related
- B. Milestone-related
- C. Order-related
- D. Cost-related
Answer: A,C
NEW QUESTION 35
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?
- A. It is converted into a reservation.
- B. It is converted into a schedule line.
- C. It is converted into a planned order.
- D. It is converted into a production order.
Answer: A
NEW QUESTION 36
Which time elements are relevant for lead t me scheduling of a product on order? Note: There are 2 correct answers to this question.
- A. Float after production
- B. Planned delivery time
- C. Setup time
- D. Total replenishment lead time
Answer: A,B
NEW QUESTION 37
Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.
- A. In the production order type
- B. In the production version
- C. In the MRP controller
- D. In the bill of materials (BOM)
- E. In the routing
Answer: A,C,E
NEW QUESTION 38
......
SAP C-TS422-2020 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Lean Manufacturing in SAP S/4HANA 8% - 12% | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. |
| Capacity Planning in SAP S/4HANA 8% - 12% | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. |
| Production Orders in SAP S/4HANA > 12% | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. |
| Process Orders in SAP S/4HANA < 8% | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). |
| Advanced Planning in SAP S/4HANA > 12% | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts |
| Demand Management in SAP S/4HANA < 8% | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. |
| Introduction to SAP S/4HANA Production Planning < 8% | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. |
| Material Requirements Planning in SAP S/4HANA 8% - 12% | Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures. |
| Master Data in SAP S/4HANA > 12% | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. |
| Introduction to SAP S/4HANA Supply Chain Planning < 8% | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. |
Prepare Top SAP C-TS422-2020 Exam Audio Study Guide Practice Questions Edition: https://www.validbraindumps.com/C-TS422-2020-exam-prep.html