Exam PSM-I Realistic Dumps Verified Questions Free [May 13, 2022]
Valid PSM-I Dumps for Helping Passing Scrum Exam!
Prerequisites
This certification exam has no formal prerequisites. The applicants don’t have to complete any training courses and hold any extra certificates. However, the individuals sitting for this test need to possess a high level of Scrum knowledge, be familiar with the Scrum Guide, and have a solid understanding of how to implement Scrum within Scrum Teams. If you are new to Scrum and have never been part of a Scrum Team, then it is recommended that you pursue one of the courses offered by Scrum on its official website. The Professional Scrum Master or Professional Scrum Foundations training courses will help you build a necessary knowledge base for the exam.
NEW QUESTION 33
When should a Sprint Goal be created? (Choose the best answer.)
- A. At any time during the Sprint.
- B. During Sprint Planning.
- C. It must be established before Sprint Planning in order to begin planning.
- D. It should have been created in the previous Sprint during Product Backlog refinement.
- E. A Sprint Goal is not mandatory in Scrum.
Answer: B
NEW QUESTION 34
When can a Development Team cancel a Sprint?
- A. When a technical dependency cannot be resolved.
- B. When the selected Product Backlog items for the Sprint become unachievable.
- C. When the Product Owner is absent too often.
- D. It can't. Only Product Owners can cancel Sprints.
- E. When functional expectations are not well understood.
Answer: D
NEW QUESTION 35
A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?
- A. Begin facilitating productive and useful Sprint Retrospectives.
- B. Comply with the decision of the self-organizing team.
- C. Consult with the Product Owner to see how he/she feels about the situation.
- D. Call a meeting between the Development Team and senior management.
Answer: A
NEW QUESTION 36
Which statement best describes a Product Owner's responsibility?
- A. Keep stakeholders from distracting the Development Team.
- B. Optimizing the value of the work the Development Team does.
- C. Managing the project and ensuring that the work meets the commitments to the stakeholders.
- D. Directing the Development Team.
Answer: B
NEW QUESTION 37
The time-box for a Daily Scrum?
- A. 15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.
- B. 15 minutes.
- C. Two minutes per person.
- D. The same time of day every day.
- E. 4 hours.
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION 38
Which topics should be discussed in the Sprint Review?
- A. The Scrum process, and how it was used during the Sprint.
- B. Sprint results.
- C. All of the above.
- D. Coding and engineering practices.
Answer: C
NEW QUESTION 39
As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?
- A. As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
- B. Inform the Product Owner at the Sprint Review, but prior to the demonstration.
- C. Reduce the definition of "Done" and get all of the Product Backlog items "Done" by the new definition.
- D. Find another Scrum Team to give the excess work to.
Answer: A
NEW QUESTION 40
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
- A. Methods of communication.
- B. All of the above.
- C. The way the Scrum Team does Sprint Planning.
- D. Its Definition of "Done".
- E. Skills needed to improve the Development Team's ability to deliver.
Answer: B
NEW QUESTION 41
Every Scrum team must have a Product Owner and Scrum Master.
- A. True. Each must be 100% dedicated to the Scrum Team.
- B. False. A Product Owner can be replaced by a business analyst in the Development Team.
- C. False. A Scrum Master is only required when asked for by the Development Team.
- D. True. Outcomes affected by their participation and availability.
Answer: D
NEW QUESTION 42
The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.
- A. True
- B. False
Answer: B
Explanation:
Explanation
NEW QUESTION 43
Which of the following are roles on a Scrum Team? (Choose all that apply.)
- A. Users
- B. Customers
- C. Product Owner
- D. Scrum Master
- E. Development Team
Answer: C,D,E
NEW QUESTION 44
True or False: When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
- A. True
- B. False
Answer: B
NEW QUESTION 45
Who isresponsible for tracking the remaining work of the Sprint?
- A. The Product Owner.
- B. The Development Team is consultation with the Product Owner.
- C. The Scrum Master.
- D. The Project Manager.
- E. The Development Team.
Answer: E
NEW QUESTION 46
A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)
- A. Providing the Development Team with detailed specifications.
- B. Interacting with stakeholders.
- C. Describing features as Use Cases.
- D. Ensuring that the most valuable functionality is produced first, at all times.
- E. Creating detailed functional test cases.
Answer: B,D
NEW QUESTION 47
A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take? (Choose the best answer.)
- A. Begin facilitating productive and useful Sprint Retrospectives.
- B. Comply with the decision of the self-organizing team.
- C. Consult with the Product Owner to see how he/she feels about the situation.
- D. Call a meeting between the Development Team and senior management.
Answer: A
NEW QUESTION 48
If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
- A. Its productivity is likely to stay the same.
- B. Its productivity is likely to decrease.
- C. Its productivity is likely to increase.
Answer: A
NEW QUESTION 49
The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.
- A. True
- B. False
Answer: A
NEW QUESTION 50
Which outcome is expected as Scrum Teams mature?
- A. There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.
- B. A Scrum Master is no longer needed since they are a mature team now.
- C. The Sprint Retrospectives will grow to be longer than 4 hours.
- D. Sprint Reviews will no longer be needed.
- E. They will improve their definition of "Done" to include more stringent criteria.
Answer: E
NEW QUESTION 51
What enhances the transparency of an increment? (Choose the best answer.)
- A. Doing all work needed to meet the definition of "Done"
- B. Reporting Sprint progress to the stakeholders daily
- C. Updating Sprint tasks properly in the electronic tracking tool.
- D. Keeping track of and estimating all undone work to be completed in a separate Sprint.
Answer: A
NEW QUESTION 52
Which technique is the best way the Scrum Master can ensure that the Development Team communicates
effectively with the Product Owner?
- A. Teach the Development Team to talk in terms of business needs and objectives.
- B. Teach the Product Owner about the technologies employed during the Sprints.
- C. Act as a go-between for them.
- D. Monitor communications between them and facilitate direct collaboration.
Answer: D
NEW QUESTION 53
......
PSM-I Exam Dumps For Certification Exam Preparation: https://www.validbraindumps.com/PSM-I-exam-prep.html
Download Free Scrum PSM-I Exam Questions & Answer : https://drive.google.com/open?id=106Ehi0NxvnhK3M7xzZ6RB5-kIUgunKkk