NEW QUESTION # 72
The amount of time that an activity can be delayed from its early start date without delaying project completion is called
- A. Negative float.
- B. Total float.
- C. Free float.
- D. Interfering float.
Answer: B
NEW QUESTION # 73
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
- A. Budget at completion (BAC)
- B. Estimate at completion (EAC)
- C. Budgeted cost of work performed (BCWP)
- D. Estimate to complete (ETC)
Answer: D
NEW QUESTION # 74
The work breakdown structure is used to organize
- A. The chart of accounts
- B. "Smart activity ID codes" representing similar items of scheduled work
- C. The smallest defined work packet
- D. Similar activity coding of schedule activities
Answer: C
NEW QUESTION # 75
What is the relationship depicted between Activity G and Activity H?
- A. Start-to-start.
- B. You cannot tell with the supplied information.
- C. Finish-to-finish.
- D. Finish-to-start.
Answer: A
NEW QUESTION # 76
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
- A. 45 lifts
- B. 150 lifts
- C. 300 lifts
- D. 450 lifts
Answer: D
NEW QUESTION # 77
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
- A. 40.
- B. 37.
- C. 36.
- D. 42.
Answer: C
NEW QUESTION # 78
Identify the late finish to develop plans and specs.
- A. 7 months.
- B. 9 months.
- C. 10 months.
- D. 8 months.
Answer: B
NEW QUESTION # 79
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
- A. 12-18-03 and 4 days of float
- B. 12-17-03 and 4 days of float
- C. 12-18-03 and 25 days of float
- D. 12-27-03 and 24 days of float
Answer: B
NEW QUESTION # 80
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
- A. 30 lifts
- B. 48 lifts
- C. 24 lifts
- D. 36 lifts
Answer: D
NEW QUESTION # 81
An early start constraint dictates
- A. The planned start of an activity.
- B. The actual start of an activity.
- C. An activity's remaining duration.
- D. The planned start of a successor activity
Answer: D
NEW QUESTION # 82
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 15 workdays
- B. 8 work days
- C. 7 work days
- D. 18 work days
Answer: B
NEW QUESTION # 83
Determine the correct formula and date for the late finish for Activity 2002.
- A. LS.2003 - 1 day -> 10-06-01.
- B. LS.2003 + 1 day -> 10-07-01.
- C. LS.2003 - 1 day -> 11.06.01.
- D. LS.2003 - 1 day -> 10-05-01.
Answer: D
NEW QUESTION # 84
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
- A. Compensable delay
- B. Excusable delay
- C. Non-excusable delay
- D. Non-compensable delay
Answer: D
NEW QUESTION # 85
How could the structural steel drawing delay have been prevented?
- A. Switch to post-tensioned concrete construction.
- B. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
- C. Allow adequate time for review and resubmittal in the baseline schedule.
- D. Add a time buffer at the end of structural steel activities.
Answer: D
NEW QUESTION # 86
When resource leveling craft labor for a critical path schedule, the scheduler
- A. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
- B. Need only consider the non-union crafts persons.
- C. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
- D. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
Answer: D
NEW QUESTION # 87
Resource planning must take all of the following into account except for
- A. Earned value techniques established for the project.
- B. Types of materials, equipment and labor skills required to complete the project.
- C. Cash flow (expenditure) limitations for completing work on the project.
- D. Time available to complete the project.
Answer: A
NEW QUESTION # 88
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.
- A. Budget at completion (BAC)
- B. Budgeted cost of work scheduled (BCWS)
- C. Estimate at completion (EAC)
- D. Budgeted cost of work performed (BCWP)
Answer: A
NEW QUESTION # 89
Which of the following is NOT required when initially planning a project?
- A. A schedule that identifies tasks required on a project.
- B. Logical relationships between the tasks.
- C. The duration of each task.
- D. Resource Identification and leveling.
Answer: C
NEW QUESTION # 90
Which of the following is NOT true?
- A. Multiple calendars can affect the total float calculation.
- B. Constraints can interfere with the longest path calculation.
- C. A network must contain only one Critical Path.
- D. Remaining durations can exceed original durations.
Answer: D
NEW QUESTION # 91
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?
- A. Drafting and Proofing the Manual.
- B. Testing, Manufacturing and Packaging.
- C. Packaging only.
- D. Printing the Manual.
Answer: B
NEW QUESTION # 92
......
AACE-PSP Exam Dumps - Free Demo & 365 Day Updates: https://www.validbraindumps.com/AACE-PSP-exam-prep.html
Free Sales Ending Soon - Use Real AACE-PSP PDF Questions: https://drive.google.com/open?id=1NUkLEQdf6Fddl1cHG1tdSsJIVU5ZvQSM