[Jan-2022] AACE International AACE-PSP Actual Questions and Braindumps
Pass AACE-PSP Exam with Updated AACE-PSP Exam Dumps PDF 2022
Planning & Scheduling Professional (PSP) Exam Certification Path
The certification path for the Planning & Scheduling Professional (PSP) Exam consists only of this Planning & Scheduling Professional (PSP) Examination. The applicants must fulfill the eligibility criteria of having at least 8 years of industry experience only or 4 years of industry experience plus 4 years of a related degree from a college.
Difficulty in Writing Planning & Scheduling Professional (PSP) Exam
All exams can turn out to be very difficult if not well prepared. The main preparation material for the Planning & Scheduling Professional (PSP) Exam is the industry experience and related college degree as this is the prerequisite of the exam and is a must for an applicant as stated by AACE. Refer to the “How to study” section above to use the official resources to best prepare for the exam. One of the key problems faced by most candidates is to choose the right research materials for their exam preparation since they use the internet to find too much data that makes it difficult for them to trust, which would be helpful for them. PSP dumps pdf are designed in such a way to make better preparatory material. This exam can turn out to be a very difficult certification if not well prepared. We always recommend studying the PSP practice dumps before actually appearing for the exam. Applicants may, however, clear the exam with the right concentration and the right preparation material.
ValidBraindumps have the most up-to-date PSP exam dumps, having a fair understanding of the question trend being asked in real certification with the help of these dumps.
NEW QUESTION 32
Each of the following accurately describes total float in a schedule EXCEPT:
- A. The amount of time an activity can be delayed without delaying the overall project completion time.
- B. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
- C. Can be positive or negative.
- D. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.
Answer: B
NEW QUESTION 33
All the following describe the critical path of a schedule EXCEPT:
- A. Changed by redefining the network logic or changing activity durations or both.
- B. Frequently defined as the shortest path through the schedule.
- C. The series of activities having the least amount of total float.
- D. Determined by network logic and is the chain of activities that controls the overall project completion time.
Answer: B
NEW QUESTION 34
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
- B. The activities occur in series with a 15-day lag.
- C. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- D. The activities run concurrently.
Answer: B
NEW QUESTION 35
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
- A. Accuracy is increased by inserting delaying events into the as-planned schedule.
- B. Not suitable for projects with long durations.
- C. Less accurate as the analysis advances through the project.
- D. Not suitable for complicated projects with multiple planned critical paths.
Answer: A
NEW QUESTION 36
Identify the minimum project duration.
- A. 19 months.
- B. 20 months.
- C. 16 months.
- D. 21 months.
Answer: B
NEW QUESTION 37
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
- A. Making "downstream" logic revisions as required.
- B. Entering the time impacts of delays and change orders.
- C. Estimating remaining durations of activities.
- D. The correct recording of actual start dates.
Answer: A
NEW QUESTION 38
For which of these delays should an owner grant a time extension?
- A. Structural steel shop drawings.
- B. Differing site conditions at parking structure.
- C. Shop drawings and centrifuge delay.
- D. Differing site conditions and centrifuge delay.
Answer: B
NEW QUESTION 39
In a "crashed" schedule, which is a chain of activities that precede activity 2004?
- A. 1001, 2001, 2002, 2003
- B. 1001, 2002, 2003
- C. 1001, 2002, 2002, 2003, 3001
- D. 2001, 2002, 2003, 2007
Answer: A
NEW QUESTION 40
What is the actual duration as of the status date or data date of Activity B?
- A. 7.
- B. 4.
- C. 0.
- D. 3.
Answer: D
NEW QUESTION 41
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?
- A. $139,000
- B. $299,000
- C. $271,000
- D. $289,000
Answer: D
NEW QUESTION 42
What is the remaining work duration of Active D?
- A. 4.
- B. 8.
- C. 3.
- D. 0
Answer: A
NEW QUESTION 43
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?
- A. The Petrochemical Industry New Plant Task Duration Handbook.
- B. The cost estimate for the plant prepared by your firm's estimating department.
- C. Industry publications.
- D. Critical path schedules prepared by you for similar completed projects.
Answer: D
NEW QUESTION 44
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-15-01.
- B. 09-08-01.
- C. 09-28-01.
- D. 09-18-01.
Answer: B
NEW QUESTION 45
A driving relationship is _____________________.
- A. The link between a predecessor and the activity whose dates it controls.
- B. A critical relationship.
- C. The link between two related activities.
- D. A finish-to-start relationship.
Answer: A
NEW QUESTION 46
What was the original planned duration for Activity A through Activity G?
- A. 28.
- B. 24.
- C. 26.
- D. 25.
Answer: A
NEW QUESTION 47
Determine the correct formula and date for the late finish for Activity 9004.
- A. LS.10002 - Lag.7 - l day -> 11-20-03.
- B. LS.10002^ Lag.7 + i day -> 11-20-03.
- C. LS.10002 - 1 day -> 11-27-03.
- D. LS.10002 + 1 day -> 11-29-03.
Answer: B
NEW QUESTION 48
......
Who should take the Planning & Scheduling Professional (PSP) Exam
This certification PSP exam test is intended for individuals with an advanced project planning experience and the production, tracking, updating, forecasting, and analysis of integrated project schedules. People who wish to be a part of AACE and lead the planning and scheduling process of their Total Cost Management framework are highly encouraged to take the exam. Before applying for this certification, applicants must have at least 8 years of related experience in the industry. Candidates with 4 years of industry experience can also apply for the exam if they have completed at least 4 years of a college degree in the same field in the past. For eligibility, applicants must adhere to AACE’s Canons of Ethics.
Latest AACE-PSP Pass Guaranteed Exam Dumps with Accurate & Updated Questions: https://www.validbraindumps.com/AACE-PSP-exam-prep.html
AACE-PSP Exam Brain Dumps - Study Notes and Theory: https://drive.google.com/open?id=1F9upwGdL-oJdNz1Fic1CoEp1FcehwMn7